SMART2 Progress - Commerce Street

Water line replacement on Commerce Street, looking east from Wick Avenue

Public Works - April 14, 2022

Water line replacement work on East and West Commerce Streets has been underway for the last several months, in preparation for paving and road redesign.

Construction on Commerce Street, between Fifth Avenue and East Federal Street, is part of Phase 2 of the SMART2 project. These blocks have been redesigned to be safer and more accessible for users of multiple modes of transportation, including motorists, pedestrians, and bicyclists. Project design features include the following:

  • Road Diet (Fifth Avenue to North Walnut Street), reducing the existing 5 vehicular lanes to 1 in each direction, plus left turn lanes, as needed.
  • Sidewalk improvements (Fifth Avenue to North Walnut Street), including landscaped amenity strip separations.
  • Safety and aesthetic improvements to crosswalks.
  • Addition of limited parallel parking (Fifth Avenue to North Walnut Street - westbound only).
  • Energy efficient and aesthetic street lighting.